OC Road Midway City
Midway City Street & Storm Drain Improvements
Here is an update for the Midway City project for November 2011:
- Utilities (telephone and gas) relocation has been completed all the streets.
- The storm drain installation has been completed on all streets except for minor
work on inlet structures.
- The street improvements concrete work (curb & gutter, sidewalk, and drive approaches
have been installed (75%) on the following streets:
- Adams Street from Bolsa Avenue to Roosevelt Avenue
- Jackson Street from Bolsa Avenue to Roosevelt Avenue
- Van Buren Street from Bolsa Avenue to Roosevelt Avenue
- Monroe Street from Bolsa Avenue to Hazard Avenue
- Jefferson Street from Bolsa Avenue to Hazard Avenue
- Wilson Street from Bolsa Avenue to Madison Avenue
- Harper Street from Bolsa Avenue to Hazard Avenue
- Washington Avenue from Beach Blvd. to Monroe Street
- Roosevelt Avenue from Beach Blvd.to Monroe Street
- The asphalt concrete base course paving has begun (60%) on the following streets:
- Adams Street from Bolsa Avenue to Roosevelt Avenue
- Jackson Street from Bolsa Avenue to Roosevelt Avenue
- Van Buren Street from Bolsa Avenue to Roosevelt Avenue
- Monroe Street from Bolsa Avenue to Madison Avenue
- Jefferson Street from Washington Avenue to Madison Avenue
- Jefferson Street from Roosevelt Avenue to Hazard Avenue
- Wilson Street from Bolsa Avenue to Madison Avenue
- Harper Street from Bolsa Avenue to Hazard Avenue
- Hazard Avenue from Monroe Street to Wilson Street
- Alleys East and West (Alley No.1 to No.10) from Adams to Newland
- The asphalt concrete finish course paving has been completed (10%)on the following
streets:
- Adams Street from Bolsa Avenue to Washington Avenue
- Jackson Street from Bolsa Avenue to Washington Avenue
- Harper Street from Madison Avenue to Roosevelt Avenue
- The parkway grass and tree installation (60%) is ongoing on various streets.
The estimated project end date based on the number of working days left is July
12, 2012.
Important Reminder!
Residents are reminded to observe “no parking signs” and to drive slowly while traveling
in construction zones to protect the contractor’s workers. It is the Department’s
sincere desire to accomplish this much-needed construction with minimum inconvenience
to the area’s residents. Your cooperation is appreciated. Please remember that construction
sites present many challenges. Please instruct children to stay away from construction
activity at all times.
Past Updates:
- Midway City Updates as of October 2011
- Midway City Updates as of August 2011
- Midway City Updates as of July 2011
- Midway City Updates as of April 25, 2011
- Midway City Updates as of March 16, 2011
- Midway City
Community Meeting Minutes: November 18, 2010
- October 22, 2010 Press Release:
Community Meeting Addresses Upcoming Midway City Street and Storm Drain Improvement
Project
|
|
|
|
|